Wet day, mainline refresher training and steady progress on 83D

A thoroughly bleak day on site it was grey, wet, and raining almost nonstop. Ideal conditions, naturally, for crew refresher training.The day started with much refuelling of the generator, and then refuelling the Baguley before refreshing on inspection, and starting procedures for the locomotive and the passenger train. Before heading out on the re-familiarisation runs […]

Busy Day Advancing Ballasting and Yard Buildings

A strong turnout on site meant plenty of progress across multiple jobs. The JCB was put to work early to shift rail and ballast in the Permanent Way Yard, improving access for the lorry due to deliver the new storage container. The container location was marked out so that photos could be sent to the […]

Baguley Finished, Gravel Completed, 83D Timbers Installed

A decidedly chilly start soon gave way to sunshine and a dry, workable day ideal for making progress across several winter projects.The final outstanding issue on the Baguley was resolved, and the locomotive was fully reassembled, bringing it very close to returning to service. Timber repairs on the Dough Wagon continued steadily, while repainting work […]

Old Track Moved, New Gravel Laid

A cool but bright and—crucially—dry day meant outdoor work could continue, even with a slightly smaller team. A potential new volunteer joined the group, adding a welcome extra pair of hands.The morning began with the JCB lifting two panels of 18‑inch‑gauge track and moving them to the upper yard, ready to be cut in half […]

Bogies Moved, Baguley Stripped, 83D End Framed

A calm, dry day meant outdoor work could continue without interruption.The morning began with moving the 18‑inch‑gauge bogies off the old tramplates and relocating them to the storage area, ready for collection later in the week. At the same time, the generator received a much‑needed refill—150 litres of diesel after running worryingly low.Work on the […]